Installation Instructions into Recessed area (thinset)



Installation into recessed area (thinset)

1. Area should be recessed the depth of the SureDome tile and the bonding material required. .







2. Apply bonding material to the bed of the area to be installed. Use an approved bonding material.





3. Brush the back of tile with a wet brush. Apply bonding material to back of tile.







4. Set the tile firmly with a good twisting motion. Base of tile must be flush with the surrounding concrete, and each tile should press directly against the adjacent tile. No space between tiles is required. With a beating block, tap tiles into place so the tiles line up with each other and the height of the sidewalk.

5. Clean off the surface with a sponge and fresh water.







6. Fill any gap between tile and concrete with a silicone sealer.